Public Works (Road Department)

◄ Back
August 25, 2017 10:00 AM

CLINTON ROAD RAMP CLOSURE

On August 28, 2017, PennDOT has scheduled the closing of the CLINTON ON-RAMP from Clinton Road onto I-376 East (heading towards the Airport and Pittsburgh) for construction. Detours will be posted to use the Clinton on-ramp to I376 west.

Please be advised that PennDOT has scheduled the closing of the CLINTON ON-RAMP from Clinton Road onto I-376 East (heading towards the Airport and Pittsburgh) for construction for August 28, 2017. There may be a delay in this closure date, but this construction will be starting soon. The closure is scheduled for 50 calendar days from the start date. Detours will be posted using the Clinton on-ramp west to the Flaugherty Run exit, turning left at the first light, and then entering I-376 east from that ramp. Large trucks/tractor-trailers may not be able to make that left, so PennDOT potentially will be posting truck detours to the Hopewell exit off I376 west.

Additionally, there will be some weekend closures of the Clinton off ramp from I376 west. These have not been scheduled but will be done as a Friday evening until Monday morning closure. The detour will again be continue to Flaugherty Run exit, turn left and merge onto Clinton exit from I376 east. As we get information, we will post any updates here.

Facebook Twitter Google Plus Email

Latest Update:

September 18, 2017 2:02 PM

SEPTEMBER 18, 2017 - PennDOT has closed the Clinton Ramp from Clinton Road to eastbound I-376 (towards Pittsburgh/Airport) this morning for construction. Anticipated re-opening is 50 calendar days (on or about November 6, 2017). Posted detour is westbound I-376 to Hopewell (Exit 48) and back onto eastbound I-376. Thank you for your patience.

Prior Updates

September 8, 2017 8:33 AM

PennDOT has advised us that the Clinton Road Ramp Closure (to EB I-376) that was scheduled for September 11, 2017 has been postponed. At this time, there is no scheduled date for construction to begin. As we're updated from PennDOT, we will post here on our website and at our Facebook page @FindlayTownshipAdmin

August 29, 2017 2:39 PM

PennDOT just advised the Clinton Road Ramp Closure project has been rescheduled to September 11, 2017. We will post any updates on our website.